City Begins Resurfacing of Cedar St./Church St. Parking Garage Top Deck on Oct. 3

Notice from the city of Santa Cruz Public Works Deptartment:

Starting October 3, the top deck of the Cedar St./Church St. Parking Garage will be under construction. Resurfacing the top deck will prolong the life of the parking garage and allow us to avoid more expensive repairs later.

The project is expected to take about 40 days during which parking on the top deck will be affected. Parking on the first floor of the garage will remain open throughout construction. Construction will be done in phases to minimize impacts to parking. The complete deck will be reopened by November 19, in time for the Thanksgiving holiday and Black Friday.

Fall is an ideal season for repaving work due to the dry, sunny weather. The City selected this timeframe, between the busy summer season and winter holidays, as a way to minimize impacts on parking during peak periods.

For questions about the project, please contact Patrick Fung at 420-5086.